Posts

Showing posts from April, 2022

Gate & Boundary Wall - update up to 30-04-2022 Leveling of Entrance gate

Park and Landscaping update 16.04.2022 to 30 .04.2022

Water Line Work - update up to - 30-04-2022 G-5 & 6 road

Storm & Rain Water- update of G-5 & 6 Road up to - 30-04-2022

Road Work Update-Commencement of Road - Interlock Tiles material Received at site 09-04-2022 to 28-04-2022

Commencement of Electric cable lying - Erection of RCC Street Light Poles & Lying Conduits for underground electrification update of 15-04-2022 to 27-04-2022

Park and Landscaping update 08.04.2022 to 15 .04.2022