Posts

Showing posts from March, 2022

Road Work Update-Commencement of Road - More Interlock Tiles reached at site 25-03-2022

Sewerage work - House Connection update up to - 25-03-2022

Commencement of Electric cable lying - update of 25-03-2022

Road Work Update-Commencement of Road - More Interlock Tiles reached at site 24-03-2022

Commencement of Electric cable lying - excavation of trenches & more Conduits for underground electrification reached at Site - update of 24-03-2022

Park and Landscaping update 15.03.2022 to 23.03.2022

Road Work Update-Commencement of Road - Interlock Tiles material Received at site 22-03-2022 to 23-03-2022

Sewerage work - House Connection update up to - 23-03-2022

Toe Wall work - G-6 up to 15--02-2022 to 22-02-2022

Commencement of Electric cable lying - Street Light Poles Received at Site 21-03-2022

Road Work Update-Commencement of Road - Interlock Tiles material Received at site 17-03-2022 to 21-03-2022

Commencement of Electric cable lying